If you have a process where you have 1. steps that need to be done in order and 2. want to make sure each steps deadline is relative to that last step, this is how you can build it. Watch video or read instructions below.

1.Build out all your steps

screen-shot-2016-11-05-at-19-34-22

2.For each step, ensure all steps have the option of ‘Make it done in order‘ in the Basics tab

order

3.For each step, in the Deadline tab, set the deadline to be X hrs/days/weeks ‘from‘ the previous step.

deadline-from

So, now, when you do a step, the next step’s deadline will now change relative to the previous step being done.

screen-shot-2016-11-05-at-19-58-48

Please contact us if you have any questions.